Article 26 of the Executive Regulations
Decision on the Excise Goods Transport Permit Request
- In force
- Decision No. 17 of 2017Executive Regulations
Summary
Governs the permit decision (silence is refusal), refusal grounds and notice, the grievance and its decision, and permit validity.
Text of the Article
a-The Ministry shall issue its decision to decide on the excise goods transport permit request under Tax Suspension Situation within (7) days from the date of its submission on the model prepared for that purpose.
b-The expiry of the period specified for deciding on the request without a response shall be considered as an implicit rejection of it.
c-The Ministry shall reject the excise goods transport permit request in the following two cases:
1-If the request does not meet all or some of the data or information referred to in the Paragraph (Second) of Article (25) of this regulation.
2-Failure to provide prior consent of the recipient licensee as stated in the Paragraph (Third) of Article (25) of this regulation.
d-The Ministry shall notify the applicant of its decision issued regarding his request - with approval or rejection - by the means established by law.
e-If the Ministry's decision to approve the transport permit request is issued, the permit should include a special number printed allowing the Licensee to transport excise goods under Tax Suspension Situation.
f-The applicant may file a grievance with the Ministry against its decision to refuse his request within (7) days from the date of the notification, or within the (7) days following the expiry of the period considered as an implicit rejection of the request. His grievance must be decided on within (15) days from the date of submission. The expiry of this period without being notified of the outcome of the grievance shall be considered as an implicit rejection of it.
g-The excise goods transport permit under Tax Suspension Situation shall be valid for a period of (15) days from the date of its issuance.
Explanation
The Ministry decides a permit application within 7 days and silence is deemed refusal; a grievance may be filed within the same short period from notice of refusal or of the deemed refusal and is decided within 15 days, which is also the permit's validity from issue; the Ministry may extend it by a similar period where necessary (Article 27(b)). On refusal, examine reasons and notice; on approval, match the consignment to the permit before departure. Issuance does not end the sender's responsibility for receipt and closure under Article 29.
Relevant to: Relevant to senders, recipients and warehouse operators in Bahrain and abroad.
Practical steps
Match goods, destination and movement date to a valid permit.
Worked example
A dispatch delayed beyond permit validity requires reviewing extension or another required procedure before movement.
Common mistake to avoid
Using an expired permit or one issued for another shipment.
Connected Articles
- Article 4 of the LawRelease for consumption
- Article 5 of the LawMovement under suspension
- Article 6 of the LawFree zones and markets
- Article 5 of the RegulationsCases of Taxation (Offer for Consumption)
- Article 6 of the RegulationsTax Suspension Situation
- Article 7 of the RegulationsPersons Obliged to Pay Tax
- Article 24 of the RegulationsTransport of Excise Goods under Tax Suspension Situation
- Article 25 of the RegulationsProcedures for Excise Goods Transport Permit Request
- Article 29 of the RegulationsClearance of the Excise Goods Transport Permit