Article 33 of the Executive Regulations
Mandatory registration
- In forcesince 1 January 2019
- Decision No. 12 of 2018Executive Regulations
Summary
The Article sets the mandatory registration threshold and the filing deadline for each trigger: counted from the last day of an actual breach month, or ending before the month of a forecast breach. Registration takes effect on the certificate date.
Official text
A.The Mandatory Registration Threshold shall be thirty seven thousand five hundred Dinars.
B.A Person required to register for Tax purposes shall apply for registration to the Bureau in accordance with the following deadlines:
1.Thirty days from the last day of the month during which the value of his annual Supplies in the Kingdom exceeds the Mandatory Registration Threshold.
2.Thirty days prior to the month during which the value of his annual Supplies in the Kingdom is expected to exceed the Mandatory Registration Threshold.
C.Registration shall take effect from the date specified on the registration certificate.
D.The Bureau shall automatically register the Taxable Person from the date his Supplies reached the Mandatory Registration Threshold if he fails to submit the application for registration within the deadlines specified in this Article. The registration provisions shall apply from such date and the Bureau shall notify him of his registration.
E.The Taxable Person shall be responsible for the Tax due on all Taxable Supplies and Imports effected prior to the date of registration where the registration was delayed in accordance with the provisions of this Article.
Explanation
Delay does not postpone liability: the NBR may register the Person from the threshold date, and the Person remains liable for VAT on all taxable Supplies and Imports made before registration.
Relevant to: Bahrain-resident businesses and their finance and compliance teams.
Fix the registration deadline
Apply the historical test at each month-end.
A resident must register if its Supplies in the Kingdom over the 12 months preceding the end of any month exceed BHD 37,500 (Law Article 29(b)(1); Regulations Article 33(a)), calculated under Regulations Article 34.
Apply the forward-looking test separately using supportable forecasts.
Registration is also required where Supplies are expected to exceed the threshold over the same period ahead (Law Article 29(b)(2)); the forecast must rest on a clear business plan (Regulations Article 34(b)).
For an actual breach, file within 30 days from the last day of the breach month.
The period runs from the last day of the month in which annual Supplies exceeded the threshold (Regulations Article 33(b)(1)); a breach in August starts the period on 31 August.
For a forecast breach, file before the expected breach month begins.
The application is filed within the same period preceding the month in which the threshold is expected to be exceeded (Regulations Article 33(b)(2)), i.e. before that month begins.
Apply the certificate effective date and deal with any delay.
Registration takes effect from the date on the certificate (Regulations Article 33(c)); if filing is late, the NBR may register the Person from the threshold date, and the Person remains liable for VAT on earlier Supplies and Imports (Regulations Article 33(d)–(e)).
Worked example
Actual breach at 31 August
If the rolling calculated Supplies exceed BHD 37,500 at 31 August, the filing period runs from that month-end. A breach expected in October instead uses the 30 days preceding October.
Key checks
The NBR may register the Person automatically from the date the threshold was reached, notifying it, and the Person is liable for VAT on all taxable Supplies and Imports made before registration (Regulations Article 33(d)–(e)). No fine is due where the application is made within sixty days after the registration period ends; where it is not, an administrative fine of up to BHD 10,000 is imposed (Article 60(a)(2) of the Law), and the delay is evasion only where no application is made within 120 days from the end of the period (Article 63(1) of the Law; VAT Registration Guide, Version 1.10, section 7).
From the date stated on the registration certificate (Regulations Article 33(c)).
Article 37(A) of the Regulations sets the minimum data a registration application must contain. It follows from this that an application cancelled for missing that data is not an application made within the period of Article 33(B) of the Regulations.
The day before the first day of the month in which supplies are expected to exceed the threshold: the period is the one immediately preceding that month (Article 33(b)(2) of the Regulations), and under the VAT Registration Guide, version 1.10, section 2.1.2, it precedes the first day of the month of expected exceedance. Where exceedance is expected in June 2026, the last day to apply is 31 May 2026, and the period of Article 60(a)(2) of the Law runs from that date.
The forward-looking test rests on all the supplies expected over the coming period, not on the new contract alone (Article 29(b)(2) of the Law); with its usual activity continuing and the contract added, the threshold is expected to be exceeded, so it must register where the expectation rests on a clear business plan (Article 34(b) of the Regulations). The application is made within the period preceding the month in which the threshold is expected to be exceeded (paragraph (b)(2) of this Article): where that month is November 2026, the last day is Saturday 31 October 2026, which moves to Sunday 1 November 2026 (Article 106(c) of the Regulations).